Capital 2 Wind Farm

The proposed Capital 2 Wind Farm is located near Bungendore in New South Wales and would be co-located with the existing Capital and Woodlawn Wind Farms. The proposed 143.5 MW wind farm will comprise 41 wind turbines which will generate enough renewable energy to power approximately 85,400 homes each year.

Development Approval for the project was granted in 2011. A Staging Plan (under Condition A13 of the Development Approval) was lodged with the DPIE in March 2018.

The Capital 2 Community Consultative Committee will be established prior to commencement of construction of the wind farm.  

A Community Fund will be payable as a Development Contribution once the project commences construction. This was agreed with Palerang Council via a Voluntary Planning Agreement in 2014 and commits to a contribution of $20,000 per wind turbine to be installed at Capital 2 Wind Farm. The Development Contribution will be payable in 3 stages once construction commences and the distribution of funds will be managed by Palerang Council.